 |
(This article was published in Transmission & Distribution World
Magazine, February, 2004 Issue.)
DVP Refurbishes Guyed Transmission Towers
In the mid 1960s, Dominion Virginia Power (DVP; Richmond, Virginia, U.S)
constructed the first operational 500-kV transmission lines in the United
States. These lines traversed a 350-mile circuitous route from the companyīs
Mount Storm Power Station in the Allegheny Mountains of West Virginia to the
Piedmont of central Virginia near Richmond. NESC heavy loading criteria formed
the basis of the new line design, but with terrain specific additions that
included a vertical loading based on radial ice thickness on the conductors of
two inches for the sections in the mountainous regions, and a 70mph hurricane
wind loading. A new family of weathering steel, lattice structureswas fabricated
to meet the design requirements. DVP used five types of suspension guyed-structures to support the conductors
in the rugged mountainous sections of these 500-kV lines.
Tower Aging and Failure Line inspections during the past few years
have revealed an increasing incidence of guy deadend grip strand failures,
probably the result of fatigue and cyclic loading, but there is no history of
failures or damage to the actual guy wires. However, following the complete
failure of an upper guy grip on an FLT-GV tower in December 2000, DVPīs
engineers began an in.house study of the problem. On Jan. 10, 2001, a FLT-GV
tower collapsed on the side of a mountain valley during a major wind storm.
During the restoration efforts, DVP shipped the failed guy grips back to the
manufacturer, Preformed Line Products (PLP; Cleveland, Ohio) for analysis.
PLPīs report concluded that, while there was evidence of long-term aeolian
vibration damage, this was not a contributingfactor to failure of the BG-4171s
on this structure. The primary cause of failure of the BIG-GRIP deadends was
"fatique caused by longitudinal cyclical loading on guying members".
The report went on to discuss the importance of maintaining a minimum everyday
tension of 10% of the strands rated breaking strength (RBS). Using PLS-CADD
software DVPīs structural engineers modeled these transmission lines and
structures. Their analysis of the actual structural guy loading, a
field-climbing inspection and in-depth file research led to the following
conclusions:
- The original guy wires were pretensioned between 3500 lbs and 22,500 lbs
each, depending on the tower type and guy wire size.
- The existing guy wire tensions are unknown. Guy grips had been replaced in
the past, and no records could be found on the reinstalled tensions or the
methods used for installation.
- The existing anchors, anchors rods and bottom adjustable hairpin anchor
connections are in good condition and can remain.
- Most of the existing guy wire is in good condition and can be reused (guy
wire samples were tested in an independent laboratory). Some guy wire had to
be replaced due to the loads developed in the PLS-CADD analysis exceeding
their design limits.
- All hardware should be replaced.
- The seat diameters for all guy grip connections, except those on the
FLT-GV, shall be increased.
Planned Refurbishment The three 500-kV transmission lines with
these structure types are vital to DVPīs service reliability and power-transfer
capability. Therefore, DVP decided to replace all guy deadend grip assemblies
and associated hardware provided by PLP. PLP provided suggestions on how to
accurately measure the tensions in the existing guys and the reinstated
tensions. DVP selected the PIAB Rope Tension Meter RTM 20D from Sweden because
it was the only device that met DVPīs requirements. The deviceīs
specifications and features include: calibration for 10 different wire sizes;
direct-digital readout for the wire tension; easy to install; and available for
2-, 5-, 10- or 20-ton applications. To comply with DVPīs tight construction
scedule, PIAB agreed to supply one of the three units to be purchased as soon as
possible, the remaining two units being delivered within six weeks. Once the
rope tension meters arrived, they were field tested on several different tower
guy systems. Guy tension values were determined by the PIAB RTMīs and then
compared with a digital dynamometerīs reading. A tension range of 300 lbs or
less was common between the devices, but DVP accepted that this difference was
reasonable in view of the magnitude of the tensions measured. DVPīs
transmission maintenance crew was responsible for replacing the guying
assemblies on those towers in "hurricane alley" in the fall of 2001.
The PIAB RTM 20D was introduced to them by using it in conjunction with a
dynamometer. After just a few guy grip installations with both devices recording
simular tension readings, the dynamometer was packed a away as the ease-of-use
and the direct load readouts available on the RTM 20D converted all skeptics.
The most impressive demonstration of the RTMīs capability came when the crew
moved to a new site and installed the RTM on the existing guy to check the
tension before beginning the changeout. The wind suddenly gusted and the
meterīs digital readout started changing to reflect the loading effect the wind
was having on the tower and associated conductors. A second crew was
added to this guy grip replacement project. Their responce to the use of the
PIAB RTM 20 D was much like the first crew, cautious and then complete
acceptance. They now have the capability of knowing the tension on a guy before
trying to remove it. It provides the information to determinate the correct
rigging for the change-out. It also was used to re-tension the guy as the
tension adjustment nuts were tightened. This project was completed in December
2003.
(This article was published in Transmission & Distribution World
Magazine, February, 2004 Issue.)
|
|